Server Migration Overview
At certain point of pushing data from your FootfallCam™ Devices to FootfallCam™ Central Servers, your organisation might decided to host the FootfallCam™ Solution onto on-premise servers. During this transition, all the data that is in FootfallCam™ Central Servers should be migrated to your own servers. FootfallCam™ offers Data Migration Service with one-time fee to perform the following jobs:
-
Software Installation and Configuration*
-
Data backup and transfer from FootfallCam™ Central Servers
-
Data restore in your servers
-
Post-migration data validation
Contact us by emailing to sales@footfallcam.com for more enquiry or/and placing the order.
Server Migration Use-case
Server Migration can be proceed with the following use cases:
-
Migration from FootfallCam™ Central Servers to client-hosted on-premise server(s)
-
Migration from on-premise server(s) to another on-premise server(s)
At the moment, FootfallCam™ does not offers migration from client on-premise server(s) to FootfallCam™ Central Servers due to technical difficulties, but will be supported in future.
Server Migration Process
During the migration, you will need to take required action in accordance to the migration stage to ensure the smooth process can be carried on.
FootfallCam™ Central Servers to client-hosted on-premise server(s)
Below shows different stage of the Server Migration Timeline, with responsibilities listed for both FootfallCam™ and for Customer to action:
Stage | Description | FootfallCam™ to Action | Customer to Action | Duration 1 |
0 | Server Provisioning and setup (Read here) |
|
|
Day 1
1hr (FFC) |
SERVICE OFFLINE 2 |
||||
1 | Data transfer and device redirection |
|
|
Day 2
2-6 hrs (depending on the network condition) |
2 | Software Installation and Configuration |
|
- | Day 2 or 3
3-4 hrs |
3 | Data restore |
|
- | |
SERVICE ONLINE |
||||
4 | Data validation |
|
- | Day 3~
1-2 hrs |
On-premise server(s) to another on-premise server(s)
There are 3 different scenario on migrating between client on-premise servers in this section:
-
Primary Server Migration - new IP address
-
Primary Server Migration - retail the same IP address
-
Secondary Server Migration
Primary Server Migration - new IP address
Stage | Description | FootfallCam™ to Action | Customer to Action | Duration 1 |
0 | Server Provisioning and setup (Read here) |
|
|
Day 1
1hr (FFC) |
SERVICE OFFLINE 2 |
||||
1 | Data transfer and device redirection |
|
|
Day 2
2-4 hrs (depending on the network condition) |
2 | Software Installation and Configuration |
|
- | Day 2~
2-4 hrs |
3 | Data restore |
|
- | |
SERVICE ONLINE |
||||
4 | Data validation |
|
- | Day 2~
1-2 hrs |
Primary Server Migration - retail the same IP address
Stage | Description | FootfallCam™ to Action | Customer to Action | Duration 1 |
0 | Server Provisioning and setup (Read here) |
|
|
Day 1
1hr (FFC) |
SERVICE OFFLINE 2 |
||||
1 | Data transfer |
|
|
Day 2
2-6 hrs (depending on the network condition) |
2 | Software Installation and Configuration |
|
- | Day 2~
2-4 hrs |
3 | Data restore |
|
|
Day 2~
2-4 hrs |
4 | Network Update | - |
|
Day 2~
1 hr (Client) |
SERVICE ONLINE |
||||
5 | Data validation |
|
- | Day 3~
1-2 hrs |
Secondary Server Migration
Stage | Description | FootfallCam™ to Action | Customer to Action | Duration 1 |
0 | Server Provisioning and setup (Read here) |
|
|
Day 1
1hr (FFC) |
SERVICE OFFLINE 2 |
||||
1 | Data transfer and device redirection |
|
|
Day 2
2-4 hrs (depending on the network condition) |
2 | Software Installation and Configuration |
|
- | Day 2~
2-4 hrs |
3 | Data restore |
|
- | |
SERVICE ONLINE |
||||
4 | Data validation |
|
- | Day 2~
1-2 hrs |